150kV UNDERGROUND TRANSMISSION LINE (UGTL) – KAFIREAS WIND PARKS PROJECT

Construction / Installation of the 150kV Underground Transmission Line between Rafina – Pallini HVC, as part of the “KAFIREAS Wind Parks” project

Length

9,5 Km

Customer
INTERNATIONAL CONSTUCTIONAL

Area
ATTICA

Contractual Price
2.642.200,0 €

Execution Period
2017-2020