400kV OVERHEAD TRANSMISSION LINE (OHTL): HVC LAGADAS – HVC FILIPPOI
Procurement of Materials and Erection / Installation of the 400kV OHTL from HVC Lagadas up to HVC Filippoi (309 Towers, 115,0 Km), including the 2 Ground Conductors (SW & OPGW) and the variation of the 400kV OHTL HVC Thessaloniki-HVC Philippoi (entrance at Philippoi Switchyard)
Contract Order: DAPM-99339
Length
115,0 Km
Customer
IPTO
Area
NORTH GREECE
Contractual Price
28.091.437,0 €
Execution Period
2014-2016