Installation of Underground Cable System 500kV DC, as part of the Project for the Electrical Interconnection between Crete and Attica
(Subcontractor of HELLENIC CABLE S.A)
Length
ATTICA 5,75 Km
CRETE 10,35 Km
Customer
IPTO / ARIADNE INTERCONNECTION
Area
ATTICA – CRETE
Contractual Price
8.092.749,4 €
Execution Period
2020-2023